Project Overview

Constructed to support three major LNG developments on Curtis Island, these temporary works enabled the efficient construction of the QCLNG, GLNG and APLNG export jetties across challenging intertidal mudflats. MLEI was engaged by John Holland Group to design three self-launching jetty travellers, providing an innovative construction solution that supported rapid, land-based jetty construction while minimising environmental impacts.

Key Project Elements

  • Design of three self-launching jetty travellers
  • Temporary work platforms supporting 280 tonne crawler cranes
  • Pile driving system for 40 metre long, 1.2 metre diameter piles
  • Installation of jetty headstocks + precast roadway units
  • Hydraulic launching system
  • Integrated piling hammer support
  • Reusable gantry system for pipe rack module installation

The completed system enabled concurrent construction of three LNG jetties, improving construction efficiency while reducing reliance on marine plant and preserving the sensitive coastal environment.

Project Info

Client

John Holland Group

Duration

2011 - 2013

Capabilities

Marine + Coastal Engineering

Structural Engineering

Market Sector

Ports + Marine

Sub-Sector

Oil and Gas terminals