Project Overview
The new bagging facility at ICL's existing Yarraville site forms part of a broader project including aggregate drive-over bins, conveyors, a dryer and warehouse.
MLEI provided above-ground structural engineering design and documentation for the 12-level steel-framed bagging tower, incorporating four material silos suspended from Level 8.
The structure was designed and detailed as modular steel assemblies, allowing sections to be fabricated with equipment installed before being transported and erected on site.
Project Info
Client
Independent Cement + Lime
Duration
2016 - 2021
Value
$15M
Capabilities
Market Sector
Sub-Sector