Kwinana Outfall Temporary Jetty
Western Australia
Project Overview
The Kwinana Power Station project required a temporary marine access structure to support installation of a cooling water outfall pipeline for the 320MW gas-fired power station in Western Australia. The works needed to provide safe access for heavy plant, pipeline installation and cofferdam operations in water depths of up to 10m.
Key Project Elements
Temporary Jetty
- 324m long temporary jetty
- Designed to support a 180-tonne crawler crane
- 27 spans, each 12m long
- Modular segments for efficient transport, assembly and removal
- Construction methodology allowing one jetty span to be built per day
Pipeline Installation
- Installation of 1,800 ID concrete pipeline
- Direct access for excavation equipment
- Spoil removal from the pipeline trench
- Pipe placement and trench backfilling
Cofferdam Works
- 20m long x 4.5m wide cofferdam driven beside the jetty
- Sheet pile driving and removal supported from the jetty
- Cofferdam removed and repositioned as pipeline works progressed
The temporary jetty gave the project team a practical construction platform in a marine environment. Its modular design supported efficient installation, relocation and removal while providing the strength needed for heavy crane operations.
Project Info
Client
Smithbridge
Duration
2006 - 2007