Project Overview

Built in 1909, the original Warroo Bridge had reached the end of its service life and could no longer accommodate modern agricultural machinery or heavy vehicles. MLEI delivered engineering heritage services and the design of a new 57 metre, three span Super T bridge that provides a safer, more resilient crossing while recognising the heritage significance of the original structure. Delivered as part of the Bridges for the Bush program, the project improves network reliability and provides a design life exceeding 100 years.

Heritage Engineering

  • Engineering heritage assessments completed to support the replacement of the heritage listed timber truss bridge
  • Site inspections undertaken to assess the condition of the existing bridge and identify project constraints
  • Heritage advice provided to inform strategic planning and future asset management
  • Engineering investigations balanced heritage conservation with modern transport requirements
  • Technical input supported the retention of the bridge's historical significance throughout project planning

Bridge Design

  • Concept and detailed design completed for the new 57 metre, three span Super T bridge
  • Integrated road, bridge, pavement, flooding and drainage design delivered as part of the replacement works
  • Durability assessments completed to achieve a design life exceeding 100 years
  • Construction support provided throughout project delivery to assist thesuccessful implementation of the design

Project Info

Client

Transport for NSW

Duration

2019 - 2026

Value

$15.3M

Capabilities

Structural Engineering

Market Sector

Transport + Infrastructure

Sub-Sector

Road Bridges

Discover more and download our capability statement

Thanks! Our Capability Statement should now open in a new tab. If it doesn’t, please check your browser’s pop-up settings and try again.
Oops! Something went wrong while submitting the form.